May 2018

During May 2018, the two units of Cernavoda NPP produced 539.891  MW (Unit 1 being in panned outage). Unit 1 registered a capacity factor of 4,4 % and Unit 2 – 98,99%. Station performance chart

February 2018

During February 2018, the two units of Cernavoda NPP produced 936.205 MW. Unit 1 registered a capacity factor of  99,47% and Unit 2 – 100,1%. Station performance chart

December 2017

In 2017 the two operating units of Cernavoda NPP produced 11.508.865 MWh, Unit 1 registered a capacity factor of 97.14% and Unit 2 registered a capacity factor of 89.72%. The station performance chart is attached

October 2017

In October 2017 he two operating units of Cernavoda NPP produced 1.044.479 MWh, Unit 1 registered a capacity factor of 96,72% and Unit 2 registered a capacity factor of 86,6%. The station performance chart is attached.

March 2017

In March 2017 he two operating units of Cernavoda NPP produced 1.058.071 MWh, Unitatea 1 being in planned outage. Unit 1 registered a capacity factor of  100,73%and Unit 2 – 100,02%. The station performance chart is attached.   The station performance chart for March 2017

December 2016

In 2016, the two operating units of Cernavoda NPP produced 11.285.924 MWh. Unit 1 registered a capacity factor of 83,78% and Unit 2 – 99,09%. The station performance chart is attached. 2016 station performance chart

June 2016

In June 2016 the two operating units of Cernavoda NPP produced 564.792 MWh, Unitatea 1 being in planned outage. Unit 1 registered a capacity factor of  13,38% and Unit 2 – 98,25%. The station performance chart is attached. Station performance chart for June 2016

April 2016

In April 2016, the two units at Cernavoda produced 1.007.673,5 MWh. Unit 1 recorded a capacity factor of 98,87% and Unit 2 –  100%. The station performance chart is attached. Station performance chart for April 2016

December 2015

In 2015, the two units at Cernavoda produced 11.639.819  MWh. Unit 1 recorded a capacity factor of 96,92% and Unit 2 –  92,23%. The station performance chart is attached Station performance chart 2015

September 2015

In September 2015, the two units at Cernavoda produced 982.591 MWh. Unit 1 recorded a capacity factor of 96,51% and Unit 2 –  97,31%. The station performance chart is attached Station performance chart for September 2015