The controled shutdown of Cernavoda NPP Unit 2

Bucharest, 23 December 2014 Press release Societatea Nationala Nuclearelectrica S.A. (“SNN”) informs that on December 23rd, 2014, Cernavoda nuclear power plant’s Unit 2 will be shutdown in a controlled manner in order to repair a defect on an impulse line related to a measurement instrument situated in the reactor building. The unit’s systems operate  in […]

The reconnection of Cernavoda NPP Unit 1 to the National Power Grid

Bucharest, 04.12.2014   Press release Societatea Nationala Nuclearelectrica S.A. (“SNN”) informs that Unit 1 of Cernavoda NPP was reconnected to the National Power Grid on 03.12.2014, at 23:21 hours. Cernavoda NPP Unit 1 was disconnected, conservatively, from the National Power Grid on 03.12.2013, following the occurrence of certain issues at the Balance of Plant (BOP). […]

Press release – The desynchronization of Cernavoda NPP Unit 1 from the National Power Grid

Bucharest, 3.12.2014 Press release Societatea Nationala Nuclearelectrica S.A. (“SNN”) informs that on December 3rd, 2014, following the occurrence of certain issues at the Balance of Plant (BOP) of Cernavoda NPP Unit 1, a conservative decision was made to desynchronize the Turbo generator from the National Power Grid, while maintaining the reactor on power. The unit’s […]

The selection of the investor for the continuation of the Cernavoda NPP Units 3 and 4 Project

Societatea Nationala Nuclearelectrica S.A.  (“SNN”) announces that China General Nuclear Power Corporation (“CGN”) has been designated the Selected Investor for the development of Cernavoda NPP Units 3 and 4 Project (“The Project”).  As well, today, October 17, 2014, the Joint Letter on the Intention to complete the Project was signed, as per this stage of […]

Re-connection of Unit 2 to the National Power Grid

Societatea Nationala Nuclearelectrica S.A. announces the reconnection of Cernavoda NPP Unit 2 to the National Power Grid on September 9th 2014; the unit will reach nominal power at 21:00 hours. Cernavoda NPP Unit 2 was disconnected from the National Power Grid on September 8th 2014, 17:30 hours, following a malfunction occurred at the electric generator, which was […]

The completion of the first phase of the investors selection procedure in view of the continuation of the Project Cernavoda NPP Units 3 and 4

Societatea Nationala Nuclearelectrica S.A. (“SNN”) announces the completion of the first phase of the investors selection procedure in view of the continuation of the Project Cernavoda NPP Units 3 and 4 (“The Project”), procedure provided in the Strategy for the continuation of the Project, approved by the General Meeting of Shareholders on August 22, 2014. […]

The initiation of the investors selection procedure for the completion of the Project “Units 3 and 4 of Cernavoda NPP”

On 27.08.2014, Societatea Nationala Nuclearelectrica S.A. (“SNN”) informs the shareholders, investors and the public on the initiation of the competitive investors selection procedure for the completion of the Project “Units 3 and 4 of Cernavoda NPP” (“the Project”), as per the Strategy for the continuation of the Project approved by the Extraordinary General Meeting of […]

The strategy for the continuation of the Cernavoda NPP Units 3 and 4 Project

Societatea Nationala Nuclearelectrica S.A. (“SNN”) will subject to the approval of its shareholders, during the Extraordinary General Meeting of Shareholders (“EGMS”) scheduled for 22 August 2014, theStrategy for the continuation of the Cernavoda NPP Units 3 and 4 Project, according to the request of the Department for Energy to amend the agenda of the EGMS. […]

World Association of Nuclear Operators visit

During June 12-13, 2014 a high level delegation of World Association of Nuclear Operators (WANO), led by the Chairman of the WANO Board, Jacques Regaldo, visited Romania for discussions with Nuclearelectrica’s top management and for a technical tour of Cernavoda NPP. The purpose of such visit of the WANO Chairman aims to further tighten relations […]