Starting the trading of Nuclearelectrica’s shares

The Bucharest Stock Exchange (BSE) informs that on 4 November 2013 the trading of Societatea Nationala Nuclearelectrica SA’s shares begins, within the Equities Section- Tier I Shares, following the favourable advisory opinion of the Trading Admission Commission (TAC) and the approval for trading by the Stock Exchange Board. The shares have the following characteristics: Symbol: SNN […]

Reconnection of Cernavoda NPP Unit 1 to the national power grid

Societatea Nationala Nuclearelectrica SA announces that the reconnection of Cernavoda NPP Unit 1 to the national power grid took place on October 30th, 2013, at 23:16. The reconnection activities were carried out in accordance with the procedures of the power plant as well as respecting the safety and protection regulations, with no adverse impact on […]

Precizari cu privire la opririle neplanificate ale Unitatilor 1 si 2

In legatura cu opririle neplanificate ale Unitatilor 2 si 1 ale CNE Cernavoda din data de 21 octombrie 2013, respectiv, 27 octombrie 2013, facem urmatoarele precizari: Opririle neplanificate sunt aferente oricarei industrii productive, inclusiv celei nucleare si nu implica niciun risc pentru securitatea nucleara, personal, populatie si mediu. Acestea sunt evenimente inerente in activitatea curenta a […]

Unit 1 shut-down

Societatea Naţională Nuclearelectrica S.A. announces that yesterday, 27 October 2013, hours 04:20 PM, because of the power supply failure of a command and control circuit, the reactor of the Cernavoda NPP’s Unit 1 automatically shut-down. All the systems response operation was in compliance with the design and no other failures were identified. During the outage, […]

Re-connection of Unit 2 to the National Power Grid

Societatea Naţională Nuclearelectrica SA announces the re-connection to the National Power Grid of the Cernavodă NPP’s Unit 2, on 26 October 2013, hours 10:40 AM. The disconnection occurred because of the stopping of a transformer supplying the plant internal services, following the failure of a relay in the transformer protection circuit. The re-connection activities were […]

Disconnection of Cernavoda NPP Unit 2 from the National Power System

The National Company Nuclearelectrica SA announces that yesterday, October 21st, 2013, Cernavoda NPP Unit 2 was disconnected from the National Power System starting with 21 :42, in order to fix a malfunction of the internal supply services transformers. During the controlled shutdown activities, the nuclear safety of the reactor, operating personnel, population and environment was not […]

Official opening of the trading session on the occasion of the Nuclearelectrica debut at BVB

The debut of Societatea Nationala Nuclearelectrica (SNN) at the Bucharest Stock Exchange (BVB) was marked by the official opening of the trading session on October 4. Mircea Ursache, vicepresident, Romanian Supervisory Authority, Daniela Lulache, general manager, Nuclearelectrica, Luisa Georgescu, one of the first employees of the company, representatives of the consortium which intermediated the initial […]

Fasciculul cu numarul 125.000

SN Nuclearelectrica SA anunta  ca sucursala sa, Fabrica de Combustibil Nuclear Pitesti, producator calificat de combustibil nuclear CANDU 6,  a realizat fasciculul de combustibil cu numarul 125 000. Rata de defectare a fasciculelor de combustibil fabricate in 2013 este 0, ceea ce reflecta  respectarea cerintelor de calitate si a normelor de protectie a mediului si securitatii nucleare. […]

Re-connection of Unit 2 to the National Power Grid3

Societatea Naţională Nuclearelectrica SA announces the re-connection to the National Power Grid of the Cernavodă NPP’s Unit 2, as scheduled, during the night between 3 and 4 July 2013, after having overhauled the pinhole that led to the minor heavy water leakage in the reactor building. All the systems have operated in compliance with the […]

Press release 06.06.2013

SN Nuclearelectrica SA anunţă reducerea cu 40% a puterii Unităţii 2 a CNE Cernavodă pentru efectuarea unor lucrări de reparaţii la unul din transformatoarele de evacuare putere. Acest echipament este în perioada de garanţie, iar intervenţia se efectuează de catre fabricant. Reactorul funcţionează în siguranţă, iar unitatea rămâne conectată la Sistemul Energetic Naţional, urmând să […]